With winter starting to express itself with fresh snow in the village, construction is proceeding apace to close the building in as quickly as possible. The concrete frame is nearly complete. The top floor is poured and the remaining work is limited to completing the lift and stair shafts to the loft level. Framing of the top floor is well advanced as many of the walls were prefabricated and roof beams are planned to commence installation this week. A floor below steel stud wall framing has commenced and is nearly complete with windows and services installed on the floor below that. The retail floor is sheet rocked and getting ready for fit out handover. The front building is closed in with the roof ready for tiles. Fit out has commenced for the RE/Max Office which will occupy two floors. Main services connections are well advanced and the stone finishing to the exterior is nearly 50% complete.

The Art program has commenced and the major commissioned works are well underway.